Enter the length and height of the wall, its doors and windows and the block you are using, and the calculator tells you how many blocks to buy with waste included, how many 80 lb bags of mortar it takes and, if you add prices, what it costs. It works in feet or metres.

Works anywhere in the world, wherever you are.

Wall measurements

For several walls, add up their lengths if they share the same height.

Typical starting sizes; change them to your openings.

Block

Nominal width × height × length. The 4, 6 and 8 in blocks share the same face (7⅝ × 15⅝ in plus the ⅜ in joint), so they give the same block count.

The CMHA (formerly NCMA) table includes about 5% for breakage and cuts. Raise it if the wall has many corners or cuts.

QUIKRETE publishes up to 13 blocks of 8 × 8 × 16 in per 80 lb bag of its Mason Mix or Mortar Mix; CMHA figures about 16. For another mix or bag, type what its label says.

Blocks to buy

151

Waste included (5%)

Wall area
160 ft²
Doors and windows
33 ft²
Block area
127 ft²
Blocks per ft²
1.125
Blocks in the wall (no waste)
143
Bags of mortar (80 lb)
11
Bags per 100 blocks
7.69

Blocks and bags are rounded up. Bags are counted from the blocks that go in the wall.

CMHA (formerly NCMA) CMU-TEC-001 and TEK 04-02A: 7⅝ × 15⅝ in block with a ⅜ in joint (8 × 16 in module). QUIKRETE Mason Mix No. 1136 (Type S) and Mortar Mix No. 1102 data sheets (rev. November 2020): up to 13 blocks of 8 × 8 × 16 in per 80 lb bag. Reviewed November 2026.

A material estimate, not a design. A structural block wall needs rebar, grouted cells and a footing set by an engineer's drawings and the building permit; this calculator does not count them, or the stucco. Confirm quantities with your contractor or supplier before you buy.

About this calculator

How it works

The wall area is length times height. The openings come off that area: each door and each window, width times height. What is left is the surface laid in block.

An 8 × 8 × 16 in block does not measure exactly that: it is 7⅝ × 7⅝ × 15⅝, and the ⅜ in mortar joint completes the 8 × 16 module, according to the Concrete Masonry & Hardscapes Association (CMHA, formerly NCMA). Each block covers 8 × 16 = 128 square inches of wall and a square foot is 144, so there are 1.125 blocks per square foot, or 12.11 per square metre.

The block width does not change the count. 4, 6 and 8 in blocks share the same 8 × 16 face, so a wall takes the same number of blocks with any of them; what changes is how thick the wall is.

A metric block uses the actual size you enter plus the joint: a 40 × 20 cm block with a 1 cm joint takes up 41 × 21 cm of wall, which is 11.61 blocks per square metre.

Waste (5% to start, the margin built into the CMHA table) is added to the blocks that go in the wall, and the total is rounded up.

How much mortar it takes

QUIKRETE's data sheets for its Mason Mix (Type S) and Mortar Mix (Type N) say one 80 lb bag lays up to 13 blocks of 8 × 8 × 16 in. That is 7.69 bags per 100 blocks: about 8.

CMHA, in its guide to estimating masonry materials, figures about 16 blocks per 80 lb bag of preblended mortar. The calculator starts with the manufacturer's figure, which gives more bags, and you can change it to whatever the bag you buy says.

The manufacturer publishes that yield only for the 8 × 8 × 16 in block. For another size, another brand, or mortar mixed on site from cement, sand and lime, enter the yield your supplier gives you.

Bags are counted from the blocks that go in the wall, without the waste: a broken block takes no mortar.

Examples

A wall 20 ft long and 8 ft high has an area of 160 sq ft. Taking out a 3 × 7 ft door and a 3 × 4 ft window removes 33 sq ft and leaves 127 sq ft. At 1.125 blocks per sq ft that is 142.875: 143 blocks go in the wall and, with 5% waste, you buy 151. For mortar, 11 bags of 80 lb. If a block costs $2.00 and a bag $12.00 (example prices), that is $302.00 in blocks and $132.00 in mortar: $434.00 in all.

A boundary wall 50 ft long and 6 ft high, in 6 in block with no openings, is 300 sq ft: it takes 338 blocks, you buy 355 with waste, and it needs 26 bags of mortar.

In metres: a 6 × 2.4 m wall (14.4 m²) in 40 × 20 cm block with a 1 cm joint takes 168 blocks; with 5% waste, 176, and 13 bags of mortar.

Why add waste

Some blocks always break in loading and unloading, and others have to be cut at corners, next to doors and windows and at the end of each course. The CMHA table includes about 5% for that.

If the wall has many corners or columns, or measurements that are not multiples of 16 inches, raise the margin: CMHA itself warns that those details increase the number of blocks and the mortar.

Important limitations

  • A material estimate, not a structural design. The rebar, the grouted cells, beams, footing and block of a load-bearing wall are set by an engineer under the building code and the job's permit.
  • It does not count special blocks (corner, bond beam or pilaster units), grout, rebar or stucco. CMHA recommends counting those pieces separately and taking them off the total.
  • Mortar bags use the yield QUIKRETE publishes for the 8 × 8 × 16 in block. Other brands, other mixes and the mason's hand change the result.
  • A wall with many corners, returns or off-module measurements takes more blocks and more mortar than the area count. Confirm quantities with your contractor or supplier before you buy.

Frequently asked questions

1.125 blocks of 8 × 16 in per square foot, before waste. In 100 sq ft that is 112.5; with 5% waste, 119 blocks, the same figure CMHA publishes in its table.

With 8 × 16 in block, 12.11 per square metre. With 40 × 20 cm block and a 1 cm joint, 11.61. If your block measures differently, choose “40 × 20 cm” and enter its actual size and your mason's joint.

With the yield QUIKRETE publishes, up to 13 blocks of 8 × 8 × 16 in per 80 lb bag, it is 7.69 bags: about 8. With CMHA's figure, about 16 blocks per bag, it would be 6.25. Check the yield on the bag of the mix you buy.

No. The width changes how thick the wall is, not the block's face: both are 8 × 16 in across the front, so the wall takes the same number of blocks. What changes is the weight, the price and, if the cells are grouted, the grout.

No. Steel and grout come from an engineer's structural design. The calculator counts the blocks and the mortar in the joints; for the concrete in a footing or a column, use the concrete calculator.